Restoration work begins on Tathra Wharf

The first stage of the Tathra Wharf restoration works has begun to ensure the wharf is enjoyed by the community and visitors for generations to come.


Tathra Wharf.

1 November 2022

The first stage of the Tathra Wharf restoration works has begun to ensure the wharf is enjoyed by the community and visitors for generations to come.

Bega Valley Shire Council Assets and Operations Director, Ian Macfarlane said the scope of the six-stage works program being delivered by contractor, GPM Marine Constructions is based on a detailed condition assessment of the structure carried out by marine engineers and divers, and in consultation with Heritage NSW.

“The works will essentially be ‘like-for-like’ and include repair or replacement of piles, structural timbers and decking, concrete footings and pads plus many ancillary items such as the hand rails, stock race and ladders,” Mr Macfarlane said.

“The scope of the works also recognises the importance of the marine ecology beneath the wharf and includes harm minimisation measures, such as seahorse relocation by accredited divers and marine growth preservation and promotion of recolonisation.”

Mr Macfarlane said the works need to be undertaken in stages as the heavy equipment being used during the restoration cannot be placed on the original unrestored wharf structure.

“The contractor will initially work from the wharf ramp, which was replaced after the 2016 east coast low damage, and then across the remainder of the wharf,” Mr Macfarlane said.

“Stage one works will involve the replacement of the stockyards and part of the stock race, as this will be used as the main public access to the wharf for fishers and visitors during later stages.

“The contractor’s work site will occupy the lower portion of Wharf Road, to accommodate demolition waste, salvaged material, new timbers, storage containers and equipment.

“Vehicle and pedestrian access arrangements will be constrained during the works, however public access to the Wharf Café, museum and part of the wharf deck will be maintained throughout the duration of the works.”

Minister for Lands and Water Kevin Anderson said the NSW Government is investing $7.81 million via Crown Lands to support the upgrade of the iconic wharf.

“This heritage-listed Tathra Wharf has become part of the character of the South Coast and this work will soon restore it to all its glory,” Mr Anderson said.

“The upgrade is supporting jobs in the region while ensuring this much-loved piece of community infrastructure can remain a drawcard for tourists and locals alike.”

The works on the iconic Tathra Wharf are expected to take approximately 12 months to complete, weather permitting.

On completion of the substructure restoration, the wharf building is set to undergo works on cladding, weatherproofing and utility services. This will require a separate heritage approval and tender process.

The Tathra Wharf restoration program is funded under the NSW Government’s COVID-19 Stimulus Package.

Was this helpful?



Making an enquiry

All media enquiries and interview requests are coordinated by Council's Communication and Events team under the adopted Communications Policy. To view this policy, visit Public Policies and search 'communications'.

To submit a media enquiry or to request an interview:


Councillors

Councillors can be contacted directly for enquiries regarding decisions of the elected Council and non-operational matters. Interviews with the Mayor should be arranged through the Communication and Events team contact details above.


Receiving information

If you’re a journalist or media organisation that would like to receive media releases and notifications about media opportunities, please email your name, title and contact details to media@begavalley.nsw.gov.au and we will add you to our distribution list.

You can also subscribe to Bega Valley Together and Business News, Council's fortnightly e-newsletters, or follow @begavalleyshirecouncil on Facebook  and Instagram.

Contact Us